Renovation
Reading a million-baht renovation quote
One San Kamphaeng estimate, sixteen trades and a roof priced in two different units.
A contractor priced the extension and renovation of a single-storey home at ฿1,013,020. Materials came to ฿676,910 and labour to ฿336,110. Those figures describe the work on one house. Dividing the total by the 75 m² on the foundation line would produce a misleading rate: the same quotation includes replacing the roof over the existing house.
Where the money goes
The extension roof and the existing roof account for ฿242,160 together. The quote also includes plumbing for three bathrooms. A second bid that covers only one bathroom or leaves the old roof in place will have a very different scope.
| Work section | Materials | Labour | Total |
|---|---|---|---|
| Structural works | ฿100,550 | ฿61,250 | ฿161,800 |
| Extension roof | ฿109,210 | ฿28,750 | ฿137,960 |
| Existing house roof | ฿79,400 | ฿24,800 | ฿104,200 |
| Blockwork and wall plastering | ฿59,900 | ฿43,200 | ฿103,100 |
| Electrical installation | ฿31,550 | ฿14,110 | ฿45,660 |
| Plumbing and drainage | ฿58,060 | ฿23,300 | ฿81,360 |
| Internal flush-finished gypsum ceilings | ฿16,275 | ฿12,150 | ฿28,425 |
| Internal flush-finished gypsum walls | ฿15,240 | ฿12,690 | ฿27,930 |
| Floor and bathroom tiling | ฿65,300 | ฿41,310 | ฿106,610 |
| Kitchen counter | ฿18,000 | ฿8,700 | ฿26,700 |
| Kitchen wall cladding | ฿4,950 | ฿6,500 | ฿11,450 |
| Bathroom sanitaryware | ฿23,475 | ฿4,850 | ฿28,325 |
| Doors | ฿40,100 | ฿8,800 | ฿48,900 |
| Aluminium windows | ฿30,000 | ฿2,700 | ฿32,700 |
| Painting | ฿19,900 | ฿30,000 | ฿49,900 |
| Clearance and cleaning | ฿5,000 | ฿13,000 | ฿18,000 |
Two questions hidden in the totals
What does a metre of roofing cover? The extension includes 190 linear metres of PU-backed sheet at ฿250/m and labour for 135 m² of roof. The existing roof lists 250 linear metres of sheet and 185 m² of installation. Ask for the effective sheet width, overlaps and measured roof area before comparing a second supplier’s rate per m².
Which total will appear in the agreement? The 16 sections add to ฿1,013,020. The written amount on the quotation reads ฿1,013,040. The ฿20 difference is small, but having a single corrected total makes later variations easier to track.
Before comparing bids
- Ask each builder to price the same drawing, fixture schedule and demolition scope.
- Confirm VAT, delivery, permits, warranty and payment stages in writing. The quotation leaves their treatment unclear.
- Check who supplies the appliances. This example prices air-conditioning circuits and separate bathroom fixtures.
Budget beyond the quote
Enter a quote, the cost of any additional work and the reserve you want to carry. The example starts at the numeric total of the case study.
Budget = (quote + additional work) × (1 + contingency ÷ 100). A 10% reserve is an editable illustration. Enter amounts on a consistent tax basis.
For a new-build comparison, enter your floor area, build rate and allowances in the house-build budget.
Location context: the project’s Chiang Mai map review records waterways and flood patches around Ton Pao in San Kamphaeng. The quote supplies no verified parcel boundary. Distance to a flood zone, road exposure and applicable land-use designation therefore remain unknown for this example.
Anonymised English transcription of a 16-section contractor bill of quantities, 24 September 2026. Figures are quoted baht amounts. The project record does not establish a final contract price or actual expenditure.