Reading a million-baht renovation quote

One San Kamphaeng estimate, sixteen trades and a roof priced in two different units.

A contractor priced the extension and renovation of a single-storey home at ฿1,013,020. Materials came to ฿676,910 and labour to ฿336,110. Those figures describe the work on one house. Dividing the total by the 75 m² on the foundation line would produce a misleading rate: the same quotation includes replacing the roof over the existing house.

Where the money goes

The extension roof and the existing roof account for ฿242,160 together. The quote also includes plumbing for three bathrooms. A second bid that covers only one bathroom or leaves the old roof in place will have a very different scope.

Work sectionMaterialsLabourTotal
Structural works฿100,550฿61,250฿161,800
Extension roof฿109,210฿28,750฿137,960
Existing house roof฿79,400฿24,800฿104,200
Blockwork and wall plastering฿59,900฿43,200฿103,100
Electrical installation฿31,550฿14,110฿45,660
Plumbing and drainage฿58,060฿23,300฿81,360
Internal flush-finished gypsum ceilings฿16,275฿12,150฿28,425
Internal flush-finished gypsum walls฿15,240฿12,690฿27,930
Floor and bathroom tiling฿65,300฿41,310฿106,610
Kitchen counter฿18,000฿8,700฿26,700
Kitchen wall cladding฿4,950฿6,500฿11,450
Bathroom sanitaryware฿23,475฿4,850฿28,325
Doors฿40,100฿8,800฿48,900
Aluminium windows฿30,000฿2,700฿32,700
Painting฿19,900฿30,000฿49,900
Clearance and cleaning฿5,000฿13,000฿18,000

Two questions hidden in the totals

What does a metre of roofing cover? The extension includes 190 linear metres of PU-backed sheet at ฿250/m and labour for 135 m² of roof. The existing roof lists 250 linear metres of sheet and 185 m² of installation. Ask for the effective sheet width, overlaps and measured roof area before comparing a second supplier’s rate per m².

Which total will appear in the agreement? The 16 sections add to ฿1,013,020. The written amount on the quotation reads ฿1,013,040. The ฿20 difference is small, but having a single corrected total makes later variations easier to track.

Before comparing bids

  • Ask each builder to price the same drawing, fixture schedule and demolition scope.
  • Confirm VAT, delivery, permits, warranty and payment stages in writing. The quotation leaves their treatment unclear.
  • Check who supplies the appliances. This example prices air-conditioning circuits and separate bathroom fixtures.

Budget beyond the quote

Enter a quote, the cost of any additional work and the reserve you want to carry. The example starts at the numeric total of the case study.

Enable JavaScript to calculate your estimate.

Budget = (quote + additional work) × (1 + contingency ÷ 100). A 10% reserve is an editable illustration. Enter amounts on a consistent tax basis.

For a new-build comparison, enter your floor area, build rate and allowances in the house-build budget.

Location context: the project’s Chiang Mai map review records waterways and flood patches around Ton Pao in San Kamphaeng. The quote supplies no verified parcel boundary. Distance to a flood zone, road exposure and applicable land-use designation therefore remain unknown for this example.